Catering Van = 91% complete

The re-building of the catering van is moving along steadily with the stainless bench tops now secured to the bench frames and the floor and pantry are complete.

The main things remaining are the exhaust fan, wheels & tyres, electrics, water, fitting the cooking equipment.

Then it will need painting and signage and it will be nearly ready to roll by early 2012.

As Nathan says, the last 10% is the hardest and longest part of the job…..